A finished park, two miles of new street, and about four fifths of a programme still on paper

Clearfield Station, and the difference between built and announced.

Clearfield never had a historic main street, because the city filled in as housing between two federal installations rather than growing out from a town centre. So it is building one. On 56 plus acres of Utah Transit Authority land beside the commuter rail platform, about $28 million went into roads, pipe and landscaping first, then a 2.25 acre park called Tower Park, then 213 apartments. The 1,000 units, the 550,000 square feet of office and the climbing gym are programme. This page keeps those two lists apart.

By Scott Buehler, Moving Utah Updated August 2026

I work Southern Utah, four hours and a mountain range away from the north end of Davis County, so these pages are researched rather than lived. What is on them was read where it is issued: the city's own parks, aquatic, public works and development pages at clearfield.city, its August 2026 newsletter, its 2024 water use filing with the state, the Utah Division of Archives and Records Service on the naval depot, the Utah Historical Quarterly account written the year the depot was sold, the codified state highway definition at le.utah.gov, the Freeport Center operator's own tenant directory, the North Davis Sewer District and the presidential remarks of January 1967. Every figure carries the date it was checked. A Davis County partner agent takes the ground level work.

The live question


How much of Clearfield Station actually exists, and how much of it is a drawing?

As of 16 August 2026 three things are on the ground. There is infrastructure, which the city's own development page costs at $28 million and describes as nearly two miles of new roads including bike lanes, along with utilities, walkways and landscaping. There is a finished public park of about 2.25 acres, named Tower Park, with an airport themed play structure, four pavilions and a public restroom, reported open by the Standard-Examiner in October 2024. And there is a first residential phase, two mixed use buildings holding 213 apartments from one to three bedrooms, which was leasing at 1342 South 950 East when this page was checked.

Everything else on the published programme is programme. The city lists approximately 67,500 square feet of commercial space, approximately 550,000 square feet of office, 1,000 residential units as townhomes and apartments and the 2.25 acre park, across 56 plus acres. Only the park and the first 213 units of that list are standing. The announced anchor commercial tenant, a climbing gym of roughly 37,500 square feet, had not been confirmed open as of August 2026. A Utah Transit Authority trustee, Beth Holbrook, speaking in October 2024, anticipated the project coming to life over the next three to five years depending on the market, which is the most honest timeline anyone attached to it has given publicly.

The reason it is being built at all is the frame for the whole city. Clearfield grew inward from two federal installations rather than outward from a town centre, so there is no historic commercial core to restore here and no old main street to make into something. What the city has instead is 56 plus acres of transit agency land around a commuter rail platform, and a decision to construct a centre on it from nothing. The companion hub carries how the city ended up in that position; this page carries what is being done about it.

The project, in numbers

56+

acres of transit agency land in the project area

$28M

spent on infrastructure before any building went up

2.25

acres of finished public park, open since 2024

213

apartments in the first vertical phase

The record


Every published element, sorted into two columns: on the ground, or on paper.

A transit oriented development publishes its finished state years before it reaches it, which makes any single description of it misleading unless the state of each element is given. Here is the whole published programme with its status as of 16 August 2026, taken from the city's own development page and from the October 2024 reporting on the park opening.

ElementWhat is publishedStatus on 16 August 2026Source
The land56 plus acres in the project area, owned by the Utah Transit Authority and developed in partnership with the cityReal, and the partnership is the reason the project exists at allClearfield City development page
InfrastructureAbout $28 million, including nearly two miles of new roads with bike lanes, plus utilities, walkways and landscapingBuilt. This is the money that went in before anything was visibleClearfield City development page
The parkApproximately 2.25 acres, named Tower Park, with an airport themed play structure, four pavilions and a public restroomOpen, reported open in October 2024, and it is the one finished public pieceClearfield City development page and the Standard-Examiner, 16 October 2024
First residential phaseTwo mixed use buildings with corner and ground floor retail, 213 apartments from one to three bedroomsStanding and leasing at 1342 South 950 East when checkedStandard-Examiner, 16 October 2024, and the operator's own leasing site
Residential total1,000 residential units as townhomes and apartmentsProgramme. 213 of the 1,000 are builtClearfield City development page
OfficeApproximately 550,000 square feetProgramme. Nothing of it is standingClearfield City development page
CommercialApproximately 67,500 square feetProgramme, beyond the ground floor retail in the first phaseClearfield City development page
Anchor commercial tenantA climbing gym of roughly 37,500 square feetAnnounced. Not confirmed open as of August 2026, so treat it as intentionReporting on the development, October 2024
GroundbreakingThe ceremony was on April 25th, in the city's own wordsHappened. The city prints no year for it anywhere on the page and none is inferred hereClearfield City development page
TimelineComing to life over the next three to five years, depending on the marketA UTA trustee's own expectation, spoken in October 2024 and quoted here with that date attachedStandard-Examiner, 16 October 2024

Checked in August 2026 at the city's development projects page and in the Standard-Examiner report of 16 October 2024. Clearfield's own station area planning submission is published by the Wasatch Front Regional Council as a scanned document with no readable text layer, so no ordinance number, plan boundary or adoption date is available and none is claimed. Development programmes change; check the city before treating any line above as current, and treat every row marked programme as an intention rather than a schedule.

The details

Where Tower Park, in the Clearfield Station project area at 1200 South State Street, beside the commuter rail platform on the west side of State Street
From City Hall About a mile and a quarter south of 55 South State Street, four minutes to drive, and that is an estimate rather than a published figure
Season Year round. It is a new open park with young planting and very little shade, which makes it a morning or evening proposition in July
Cost Free. The park, the paths and the plaza are public; the commuter rail platform beside it is fare controlled and is the transit agency's
Time needed Half an hour for the park and the platform, and rather more if there is a child and a play structure involved

Getting there

From City Hall the run is straight south down State Street to about 1200 South, with the project area on the west side. Coming off the interstate, exit 334 puts you on 700 South a short distance north of it. The commuter rail platform is the landmark, and if you are arriving by train you are already inside the project area when you step off. Parking is on the project's own new streets rather than in a single lot.

Before you go

  • The park is finished and the rest of the site is not. Expect construction traffic, site fencing and half built streets around a complete public space, which is an unusual combination to walk into.
  • The play structure is airport themed, which is a deliberate nod to the installation on the other side of the city rather than a coincidence.
  • This is the county's only place where a finished public park sits directly beside a commuter rail platform. If you are testing whether the train works for a household, it is the obvious place to do it.
  • Nothing on the published programme beyond the park and the first residential phase exists yet. Do not plan a visit around the commercial or office space.

The frame


Most Utah cities restore a main street. This one has to build the first one it ever had.

Set this project beside what other cities in this county are doing and the difference is structural rather than a matter of taste. Farmington has a courthouse and a nineteenth century street grid. Bountiful has a tabernacle and a main street. Kaysville has a rock building and a run of listed houses on one road. Clearfield has none of that, because the century that made the other towns was the century in which this one was farm ground, and the decade that made this one was the 1940s, when it filled in as housing between a naval depot and an air field.

That is not a criticism of the place and it should not be read as one. It is a description of a settlement pattern, and it has a direct practical consequence: there is no historic district here to convert into a walkable centre, no block of old shopfronts to reoccupy, and no building stock from before the war in any quantity. A city in that position that wants a centre has to buy or partner for the land and construct one, and the only large piece of well located land in the middle of Clearfield belongs to the transit agency.

Hence the shape of the deal. The Utah Transit Authority holds the ground around the commuter rail platform, the city partnered with it, and about $28 million went into roads, pipe and landscaping before a single vertical element appeared. That order of operations is the honest measure of what building a downtown from nothing costs: two miles of new road, with bike lanes, laid out on ground that had no streets on it at all.

Whether the result becomes a centre in any meaningful sense is not knowable yet and this page is not going to pretend otherwise. A 2.25 acre park, 213 apartments and two miles of new road is a real beginning and it is also about a fifth of the published programme. The most useful thing to do with a project at this stage is to go and stand in it, which takes half an hour, and to check the city's development page for the current position rather than reading any description of it, including this one. The mover page carries what this means for a household weighing an address nearby.

Two miles of new road and twenty eight million dollars of pipe, laid on ground that had never had a street on it, before anyone poured a foundation.

The other one


There is a second project on the west side, and the city says it includes a beach and a kayak launch.

Lakeside Square sits on the west side of Mabey Pond and it is the less publicised of the two. The city publishes a northern section of 296 residential units, 26,500 square feet of commercial space and 16,500 square feet of community space, the last of which it describes as including a walking path, a beach, a kayak launch, a plaza and event area, an art plaza and open space. Construction of the northern section is given as running from autumn 2023 through 2026. The southern section is in design and described as five or more years out.

A city built beach and kayak launch on a pond in Clearfield is the sort of thing nobody expects and the city publishes it plainly, so it is recorded here as published rather than as delivered. Mabey Pond itself belongs to the county subject rather than to this page: the lakeside parks page carries every water edge in the county with its hours, its rules and the state fishery limits that apply to it, and Mabey is on that list. What this page carries is the development on the bank.

Two other projects appear on the practical city guide and did not appear on the city's own development page when it was checked in August 2026: a mixed use scheme of about 6.92 acres with 55 townhomes near 175 West Antelope Drive, which had hearings in December 2025 and January 2026, and an apartment project named for the highway. They may have completed, been withdrawn or moved, and none of the three possibilities can be distinguished from the outside, so neither is described here as live.

The general point for anybody reading development news about this city is that the pipeline is unusually large relative to the population. A city of about thirty two thousand people with roughly 1,300 residential units in two published programmes is proposing to add a noticeable fraction of its own housing stock, most of it attached and most of it on ground that has never held housing. That is a real thing to weigh, in either direction.

The city publishes a groundbreaking date with no year on it, and the largest numbers in this project are programme rather than construction. The development page states that the Groundbreaking Ceremony was on April 25th, meaning the project is underway, and no year appears anywhere on that page. There is no anchor inside the text from which to derive one, so this companion prints the fact and not a year, which is what the city actually says. The same discipline governs the rest: 1,000 residential units, 550,000 square feet of office, 67,500 square feet of commercial and a 37,500 square foot climbing gym are published intentions, and 213 apartments, a 2.25 acre park and about two miles of road are what stands. Anyone told that a completed downtown is arriving on a date should ask which of those two lists the promise comes from.

Living with it


A construction site with a finished park in it, for the next several years.

For a household weighing an address within walking distance of this, the practical position is straightforward and it is a trade. What is there now is a good public park, a commuter rail platform and two miles of new street, with construction around them. What is coming, on the published programme, is several years of building activity followed by a substantially denser piece of city than anything else in Clearfield. Whether that is an argument for or against a particular street depends entirely on which of those two states you are buying into, and the honest answer is that you are buying into both in sequence.

The transit piece is the part that is real today and easy to test. The commuter rail platform is inside the project area, the park is beside it, and half an hour on a weekday morning will tell you whether the service works for a specific household better than any published frequency table. That is a genuinely unusual thing to be able to test on foot in a Utah city of this size.

The other thing worth saying plainly is that this project is the city's answer to a structural problem rather than an ordinary subdivision. It exists because there is no historic centre here to work with, which is a fact about the 1940s rather than about anybody's planning. The rest of that story, including the depot that took the west side and the road that runs to the installation on the east, is on the depot page and the highway page.

Finally, the boring but load bearing advice. Development programmes of this size change, phases slip, anchor tenants move and unit counts get revised, and none of that reaches a property listing quickly. Read the city's own development page before relying on anything, including anything above, and treat renderings as what they are. The mover page has the rest of what an address in this city asks for.

Quick answers


Clearfield Station, answered.

A transit oriented development on 56 plus acres of Utah Transit Authority land around the commuter rail platform at 1200 South State Street, built in partnership between the city and the transit agency. The city publishes a programme of approximately 67,500 square feet of commercial space, approximately 550,000 square feet of office, 1,000 residential units as townhomes and apartments, and an approximately 2.25 acre park, supported by about $28 million of infrastructure including nearly two miles of new roads with bike lanes. It is the city's answer to never having had a commercial centre of its own.

As of 16 August 2026, the infrastructure, the park and a first residential phase. The park, Tower Park, is about 2.25 acres with an airport themed play structure, four pavilions and a public restroom, and was reported open in October 2024. The first vertical phase is two mixed use buildings holding 213 apartments from one to three bedrooms, which was leasing at 1342 South 950 East when this page was checked. The 1,000 unit total, the 550,000 square feet of office, the 67,500 square feet of commercial and the announced climbing gym are published programme rather than construction.

The city's own development page states that the Groundbreaking Ceremony was on April 25th and meaning the project is underway, and it prints no year anywhere on that page. There is no anchor inside the text from which to derive one, so no year is printed here either. What can be said with a date attached is that the public park was reported open in October 2024 and that a Utah Transit Authority trustee, speaking that same month, anticipated the project coming to life over the next three to five years depending on the market.

Because it does not have one to restore. The air field on the eastern boundary began construction in 1940 and the naval supply depot on the western side was commissioned in 1943, and the residential grid between them filled in as housing rather than growing outward from a commercial core. That means no historic main street, no block of old shopfronts and very little pre war building stock of any kind. A city in that position that wants a centre has to construct one, and the largest well located piece of land in the middle of Clearfield belongs to the transit agency.

The finished public park inside the Clearfield Station project area, of approximately 2.25 acres, with an airport themed play structure as its centrepiece, four pavilions and a public restroom. It was reported open by the Standard-Examiner in October 2024. It is the one completed public element of the development and it sits directly beside the commuter rail platform, which makes it the easiest place in the county to test whether the train works for a particular household. The planting is young and there is very little shade, so it is a morning or evening park in high summer.

A second mixed use development, on the west side of Mabey Pond. The city publishes a northern section of 296 residential units, 26,500 square feet of commercial space and 16,500 square feet of community space, the last described as including a walking path, a beach, a kayak launch, a plaza and event area, an art plaza and open space, with northern section construction running from autumn 2023 through 2026. The southern section is in design and described as five or more years out. Mabey Pond itself is carried by the county's lakeside parks page rather than here.

On the two published programmes together, roughly 1,300 residential units: 1,000 at Clearfield Station as townhomes and apartments, and 296 in the northern section of Lakeside Square. In a city that counted 31,909 people at the 2020 census, that is a noticeable fraction of the housing stock, most of it attached and most of it on ground that has never carried housing. How much of it gets built and when is exactly the thing nobody can answer from outside the process.

There is a submission, and it could not be read. Clearfield's station area planning document is published by the Wasatch Front Regional Council as a scanned file with no readable text layer, which means the adopted ordinance number, the plan boundary and the statutory framework behind it are all unavailable from that source. No claim about any of the three appears on this page as a result. If a plan boundary matters to a decision, ask the city directly rather than working from any secondary description of it.

It was announced as the anchor commercial tenant at roughly 37,500 square feet and had not been confirmed open as of August 2026. Treat it as an intention rather than as a facility until the operator or the city says otherwise. The same applies to the wider commercial and office programme: beyond the ground floor retail in the first residential phase, none of the published 67,500 square feet of commercial or 550,000 square feet of office is standing. Check the city's development projects page for the current position before planning anything around it.

Scott Buehler, Moving Utah

A finished park, two miles of road, and about four fifths of a plan still on paper.

The useful way to read this project is to keep two lists apart and to go and stand in it for half an hour. The park is real, the platform is real, the first 213 apartments are real, and the streets are in. The thousand units, the office space and the climbing gym are intentions with no date attached that anybody has published. If a street near the project area is on your list, walk it, ride the train once, and then read the city's development page rather than a rendering. Tell me what you are weighing and I will introduce you to a Davis County partner agent who is watching this build, and stay on the file for the financing side.

Referral disclosure. Outside Southern Utah, I connect home sellers and buyers with partner agents I trust in their area. If you choose to work with an agent I refer, that agent's brokerage pays my brokerage (Real Broker, LLC) a referral fee. The fee comes out of the agent's compensation; it is not an added cost to you. You are always free to choose any agent you wish, and using a referred agent is never required.